STAGE 02 - Apply for a building warrant

Building Warrant FEES

The warrant application should include sufficient information to allow the verifier to check for compliance with building regulations.

If a warrant application is submitted without the appropriate fee it should not be accepted.

If the appropriate fee is provided and it appears to the verifier that all of the information is present the application can be accepted. However, if all the information is not submitted the verifier may, when appropriate, accept the application with the condition that the applicant submits the information within 42 days from the date of receipt.

If the requested information is not submitted within 42 days, the verifier may consider the application withdrawn and return the application and fee to the applicant. The conditional acceptance of an application should only be used to prevent applications lacking key pieces of information having to be rejected immediately.
 